Tuesday, 19 February 2013

Latest Update from CSW Broadband

The Coventry, Solihull & Warwickshire Superfast Broadband project team has produced a briefing on the latest developments in the plan to bring superfast broadband to homes in the county. The briefing is set out below:
CSW Broadband Project Gets Results
A project that aims to improve broadband across Warwickshire has made improvements in some areas before a penny of the project budget is even spent. CSW Broadband has been gathering information from communities about the broadband challenges that they face and where the local infrastructure, such as communications cabinets, are located. As a result of the information received the project has been able to convince BT to upgrade cabinets at Coton Park in Rugby and at Warwick Gates so that those communities are now able to access superfast broadband. Furthermore, as a result of information received from parishes around the county a further 45,000 properties are now to be included in the commercial broadband roll-out, meaning that the project funds can be utilised to help more communities in harder to reach areas.

Looking ahead, the contract should be awarded in May of this year, and then the work can start on the design of the network. The solution chosen will depend to a large extent on which bidder is successful as they use different technologies, but in any event roll-out should start this year and is due for completion by 2015.

CSW Broadband still needs businesses, individuals and community champions to engage with the project. There are areas where the levels of survey returns are quite low. This may be because there is little demand for faster broadband, or it may simply be that everyone is assuming that someone else is taking action. It will be easier to justify investing in those areas that show a high level of demand than in those were there appears to be little requirement. This has been evidenced by the fact that it is those areas that have been most active in completing the surveys that have now been included in the commercial roll-out. For more information about the project, including maps showing where surveys have been completed and the surveys themselves, please visit CSW Broadband.

Wednesday, 28 November 2012

Fosse Division Community Forum - 22 November

Last Thursday evening, despite the wind and rain, I attended the quarterly meeting of the Fosse Division Community Forum, held in Wolvey. Also attending from the parish council were Councillor Stephen White and the clerk, Margaret Cartwright.

The meeting received a presentation from the Rugby Rural North Safer Neighbourhood Team on local issues they've been involved in during the past few months, along with a report back on the three local policing priorities identified at the last meeting. None of these related to Shilton/Barnacle area.

However, in identifying the local priorities for the next three months, Stephen White referred to concerns regarding speeding traffic in Leicester Road, Shilton. This had been a matter that a local resident had recently contacted the parish council about, and it was therefore put forward as a matter that deserved extra attention. Fortunately, the forum agreed to adopt this as one of the three local priorities, and therefore the local Safer Neighbourhood Team will be visible during the next three months seeking to slow speeding traffic entering the village along Leicester Road. The on-going work the police are doing on this issue can be viewed here.

The forum then received two of its regular updates: from Leigh Hunt from Warwickshire County Council on the superfast broadband project, and from Anna Rose from Rugby Borough Council on planning issues and developments. A number of briefing notes were circulated with information on matters on interest, including the progress on a gypsy and traveller site allocations development plan, quality control monitoring of the highways maintenance teams, and the Warwickshire Director of Public Health's 2012 annual report (the video at the bottom of this post is of Dr John Linnane introducing his report).

The next meeting of the Fosse Division Community Forum will be on Thursday 14 March from 7.00pm at the Village Hall in Monks Kirby.

Wednesday, 10 October 2012

Superfast Broadband Project Update - October Newsletter

The latest newsletter from the Coventry, Solihull & Warwickshire Broadband Project Team has just been released. The focus this month is the procurement stage, where the team will be starting discussions with potential suppliers to better understand the infrastructure currently in place and where suppliers are intending in make investment themselves during the next three years.

The latest timetable for the project is also interesting. The next key date for me is between November - December this year when there will be a public consultation on the so-called 'intervention areas' (ie. those areas of the region that will require public subsidy to achieve superfast broadband because the commercial market itself does not consider it cost effective to make investments there).

This is the latest newsletter in full:
A reminder of what we are trying to achieve
The Coventry Solihull Warwickshire (CSW) Superfast Broadband Project aims to deliver the Government’s 2015 targets, as set out in the December 2010 strategy document 'Britain’s Superfast Broadband Future' that every premise should be able to access broadband at speeds of at least 2Mbps, and that superfast broadband (defined as providing more than 24Mbps) should be available to 90% of premises in each local authority area. The intention is to procure open access wholesale network services that:
  • any internet service provider can use to deliver retail superfast broadband services to residential and business customers;
  • can assist businesses by helping to connect premises and mobile workers to the services they require;
  • can assist any public sector organisation in building Public Services Network (PSN) compliant infrastructure;
  • any community network can use for backhaul.
Our aspirations beyond 2015 are in keeping with the European Commission’s 2020 targets that fast broadband coverage at 30Mbps should be available to all EU citizens, with at least half European households subscribing to broadband access at 100Mbps. The project will endeavour to deliver infrastructure and services that can scale appropriately to keep pace with the increasing bandwidth demands of new applications and services.

Pre-procurement phase has started
The project has now passed the B-zero gateway which was a significant achievement and reflects the amount of hard work that we (and our Community Champions) have been doing over the past few months to really understand the true state of broadband in our area. We now have the go-ahead from BDUK to enter the pre-procurement phase of our project and can start to engage with suppliers in readiness for a full procurement exercise (see timetable below). This is great news and means that we now enter an exciting time as the project starts to become very real.

However there is still the issue of State Aid to be dealt with. We are informed by BDUK that the EU should be giving its approval for the UK to set up a National Competency Centre “imminently”. This means that rather than the EU dealing with approval requests from all of the UK projects individually, they will be dealt with at a UK level, which should speed up that part of the process.

Our timetable for the project
The following indicative timescales are determined by BDUK with the stages following a prescribed process, subject to the State Aid issue being resolved:

October – November 2012: Open Market Review
Includes 4 weeks to engage with all suppliers and learn their future roll-out plans, and 2 weeks to update our coverage maps

November – December 2012: Public Consultation
Publish maps of our intervention areas and invite comment

December 2012 – January 2013: Initial State Aid Application
Results from the Open Market Review and Public Consultation used to refine our intervention area

January 2013: Issue final Invitation to Tender
This will go out to the two approved contractors on the BDUK framework – namely BT and Fujitsu

April 2013: Preferred bidder choice signed off by Warwickshire County Council Cabinet
A required formal process

May 2013: Contract awarded
We will work with the successful bidder will start designing our network.

October 2013:Stage sign-off

November 2013: Commence Phase One roll-out
We will be actively testing the solutions throughout this phase.

February 2014: Commence full roll-out

March 2015: Full roll-out phase sign off

As stated above – these are indicative timescales only. Full updates will be given as the project progresses

Open Market Review (OMR)
The OMR is intended as a precursor to a formal public consultation document. The OMR, in contrast to the public consultation document, is not a specific requirement under the European Commission’s Broadband Guidelines. However, we consider that early market engagement at this stage is an essential and extremely important part of our early market research. The results of the OMR will assist us with understanding the broadband infrastructure (basic broadband and Next Generation Access (NGA)) already in place and where there are definite plans for investment in such infrastructure in the coming three years and is a significant step in the design of our intervention area.

We are sending the OMR to all known broadband infrastructure and internet providers in our area. It can also be downloaded here.

We invite responses from any broadband infrastructure and internet providers in our area. All responses (as detailed in the OMR document) should be received by Friday 26th October 2012.

We have also provided coverage maps and a list of postcodes for the sub-region which you can access here:

http://www.cswbroadband.org.uk/suppliers/procurement/omr-state-aid-sfb-map/

http://www.cswbroadband.org.uk/suppliers/procurement/omr-state-aid-usc-map/

http://www.cswbroadband.org.uk/documents/OMR%20Postcode%20Lists%202012-10-01.pdf

http://www.cswbroadband.org.uk/documents/OMR%20Postcode%20Lists%202012-10-01.xlsx

The maps, which are fully zoomable, illustrate our current assessment of the State Aid status (white, grey, black) for each postcode area in the region – pink has been chosen to represent the “white” areas. The boundary of the region is shown by a thick red line and the area outside the boundary is the buffer area required by State Aid where communities either side of the boundary may benefit from upgrading the infrastructure. The coloured dots on the map represent both business and residential premises, with the different colours highlighting our current estimate of the distance of the premise from existing infrastructure (green is near, hence good, red is far away, hence bad).

You will see this evolve as we gather more information from people filling in surveys and crowdsourcing the existing infrastructure.

The postcode list covers all postcodes in the mapped area. The data is derived from the OS AddressBase Plus dataset released in August 2012.

Surveys and data collection
The survey responses that we have collected so far will provide crucial data to assist in our supplier engagement. We are all aware that Internet Service Providers will advertise and sell a service on an "up to" speed basis - in other words you are unlikely to achieve the headline speeds that are advertised. The survey responses that we have received have enabled us to build a partial picture of what the actual speeds are in many places in Coventry, Solihull and Warwickshire.)

However, we do have some significant gaps in our data and we do need to develop a much fuller picture. So, we would ask all of our Champions and individuals to redouble your efforts to ensure that we get 100% coverage of our survey data so that when we enter into negotiations with suppliers we will be smart clients and can show the picture as it really is rather than as we may be told it is.

Top questions this month:

Q1. When will you know what speeds I will get?

There are so many variables - right down to the wiring in your home or office - that until the roll-out is complete it will be impossible to say exactly what speed any particular property will achieve. However we will be working with our chosen supplier to design a network that will address the issues that we have discovered during our many months of public consultation and data gathering. When we do go out to tender we be using a performance-based specification rather than requiring particular technologies, so it will be up to the bidders to use their expertise to achieve our targets of 100% coverage at a minimum of 2Mbps and 90% at 24Mbps or above.

Q2. Does this mean we don’t need to do the surveys any more?

It is now more vital than ever that we get full coverage with our surveys. Throughout our tendering and design phase we will be looking to achieve best coverage for every area, and we cannot do that unless we know what speeds are actually achieved in each area and what the possible future demand for faster broadband might be.

Q3. I am a community broadband provider – what does this mean for me?

Our project aim is to provide a wholesale broadband network. That means that any ISP can provide services over the network. We have also stated our intention to get fibre as close to every community as possible because that is the best way to provide future resilience. Therefore the final network should provide affordable backhaul for community broadband providers.

CSW Broadband now on social media – come and join the conversation
We are now on the major social media channels and are already creating a buzz. Join in for up-to-date information and an opportunity to influence how the project develops:


Facebook
Twitter
Linkedin

Sunday, 25 March 2012

Shilton Parish Council Chairman's Report to the Annual Parish Meeting 2012

For those who missed it, here is the annual report of the Chairman of Shilton Parish Council, Councillor Bill King, that he gave to the Annual Parish Meeting held last Thursday night:
  • Emma Raymont was appointed Clerk on 1 April 2011. During the year, she has done various courses working towards her qualifications necessary to help the parish council become a Quality Council.

  • Land in Ash Tree Grove is now owned by the parish council after many years of negotiation. We have drawn up plans for the maintenance of the area, in consultation with the residents. The hedge along the roadway has been cut back.

  • Ken Gupwell is now looking after the cemetery for the parish council and we are all very pleased with the care he is giving to it. Jackie Essex is now advising the parish council and looking after the records for the cemetery.

  • The netting along the road side of the playing field should be erected soon and work on the hedge will begin as soon as possible after that. Ron Lissaman and Mike Randall have been in charge of looking after this work.

  • Planning permission for travellers at Top Road was turned down by Rugby Borough Council, but they have appealed. There was a hearing in December, which was adjourned until February, and then this one was adjourned and will now be heard in June. 

  • CCTV is now up and running in the car parks at the village hall and the pavilion. This can only be accessed by the police at the request of the parish council.

  • Dan Essex, Stephen White and Emma Raymont have formed a committee which is working towards Shilton Parish Council becoming a Quality Council.

  • The Shilton & Ansty Trust, of which I am a trustee, has awarded a number of grants this year to people in the villages of Shilton, Ansty and Barnacle.

  • We have spent over £1,000 repairing the wall around the cemetery during the year.

  • The parish council is investigating what effect the Localism Act will have for the parish council.

  • Participatory Budgeting, where local people can suggest ways of spending some of the council's money, is one of the things we are looking at.

  • The parish council arranged a meeting with all the local organisations to arrange festivities for the Queen's Diamond Jubilee. This committee is now called the Jubilee Committee, and is chaired by Pat Hemmings. Festivities will take place on Sunday 3 June at Shilton village hall and on the playing fields, which will include field games and a pram race, hog roast and tea for the children. There will be music and entertainment throughout the afternoon and early evening, and then on the evening of Monday 4 June in Barnacle village hall. Mugs, which have been paid for by the parish council, will also be distributed to all children aged 16 years and under who live in Shilton and Barnacle.

  • There will be an election in May to elect Shilton parish councillors and Rugby councillors. The boundaries have been changed for Rugby Borough Council and we will in future be Wolvey & Shilton, which will only have one councillor instead of the two we have now. A number of the present parish councillors are not standing for re-election, and we will therefore be looking for new people to stand for election to become parish councillors. The council will only stand for two years, and there will then have to be another election, after which we will be in line with other councils in Rugby and the council will then be elected every four years.

  • Dan Essex has been looking into various schemes that are available to improve broadband in the villages.

  • Thank you to all the parish councillors for all their hard work over the last year. Thank you especially to Ron Lissaman and Mike Randall, who have done a lot of work for the council over a number of years and are not standing for re-election, and to Jean Russell-Pattinson who retired from the parish council last year. 

Friday, 10 February 2012

Parish Council Meeting - 7 February

On Tuesday night, I chaired the February meeting of Shilton Parish Council.

As usual, the meeting started with updates from county councillor Phillip Morris-Jones and borough councillor Tony Gillias on recent developments at the Shire Hall in Warwick and the Town Hall in Rugby.

I was particularly interested to hear Councillor Gillias report that on the previous night, Rugby Borough Council's Cabinet had agreed to contribute £246,000 to the funding that had been provisionally allocated to support improved broadband within the borough. I have blogged about this project on a number of occasions and am particularly keen to see broadband line speeds in Shilton and Barnacle improve considerably to that that was currently provided.

Out of total Government funding across the country of £530m for this project, Warwickshire has been allocated £2.95m in order that superfast broadband, with line speeds of greater than 24Mbps, is made available to 90% of homes. The Rugby borough area has been awarded £246,545, which needed to be match-funded from other sources in order to release the Government cash. Thankfully, the funding allocated earlier in the week by Rugby Borough Council has done this, which will ensure that at least £500,000 will be spent improving broadband speeds locally. This is likely to increase further by attracting additional private sector funding.

I'd recommend anyone interested in this subject to read the report that was submitted to the Cabinet meeting on 6 February (if you can overlook the irony of downloading a 32Mb file with broadband line speeds not fit for the purpose, it's agenda item no. 8!). I was particularly pleased to see a recognition within that report of the problems that poor broadband speeds pose for people living within the rural part of the borough. The report highlighted this, saying:

With Rugby town receiving the majority of the benefits from private investment, this has become an issue of rural development.

As private residents in rural locations are those who may find it most difficult to take advantage of face to face services at the Town Hall, channel shift to online services would seem natural. Without access to broadband services however, they may be unable to access such channels, disadvantaging them further.

Limited access to broadband services in rural locations will impact the borough's ability to attract commercial organisations.
The approval of this match-funding shows good progress is being made, and I shall continue to follow developments closely.

The parish council was also able to confirm what each household will be paying towards its expenditure for 2012/13. As you'll know, an element of the Council Tax bill goes towards the parish council's costs for the year. In December, the council agreed to set its budget at £16,200, and now Rugby Borough Council has informed us as to how this will be reflected within the Council Tax bills that will be hitting doormats soon. Depending on which band your house is in, the parish council's element of the bill will come to:

  • Band A - £30.35
  • Band B - £35.40
  • Band C - £40.46
  • Band D - £45.52
  • Band E - £55.64
  • Band F - £65.75
  • Band G - £75.87
  • Band H - £91.03
This will be a small increase compared to what households paid this year (due largely to taking account of inflationary increases to our costs), but I still believe that at less than 88p a week for a band D equivalent property, the parish council remains good value. Of course, it should also be remembered that added to this amount will be the precepts that are to be levied by Warwickshire County Council, Warwickshire Police Authority and Rugby Borough Council.

Elsewhere on the agenda, there was the usual review of financial matters, comments on recent planning applications that had been submitted, progress updates on a number of projects that were on-going, and consideration of what action could be taken in response to a range of concerns that had been raised during the past month by local residents.

The meeting finished at 10.00pm on a bitterly cold winter's evening, and the next meeting of Shilton Parish Council will be held on Tuesday 6 March at 7.30pm at the Parish Council Meeting Room, Church Road, Shilton.

Sunday, 16 October 2011

Superfast Broadband Update

I'm following with interest the campaign being lead by Warwickshire County Council to bring superfast broadband to those parts of the county that currently struggle with slow download speeds. A regular newsletter is now being published in order that residents can keep up to date with how the project is going, and I have reproduced the first of these newsletters below:
Project Update
Since the announcement that the Government was to make £530m available for the provision of superfast broadband in the rural areas, there have been a succession of follow-up announcements. We are seeking clarification on a number of issues, but this is the position as we currently understand it.

Funding
The Government is making £4.07m available for Coventry, Solihull and Warwickshire. There is a requirement that this amount should be match-funded from local authority capital funds, which is challenging given the current economic climate, although the spend can be spread over a number of years.

Ambition
The Government ambition is to provide a minimum of 2Mbps broadband to all homes, and superfast broadband to 90% of people by 2015. Superfast broadband has been clarified to mean at least 24Mbps. Coming behind this is an EU requirement that by 2020, fast broadband coverage at 30Mbps should be available to all EU citizens, with at least half European households subscribing to broadband access at 100Mbps. Clearly, this is a significant uplift coming just a short time after the UK targets and this will have implications for the Local Broadband Plan.

Progress
We are still actively collecting data (see below) and hope to submit the Local Broadband Plan to Government in April next year. This document should show how we propose to improve broadband speeds across the whole of the sub-region, not just the rural areas, although it is only the rural areas that will receive Government funding.

What can you do to help? How good is your broadband?
A key component of your Local Broadband Plan will be evidence of where specific problems exist across the sub-region. We therefore have to map this information and in order to do that we need your help. If you have not already done so please complete the broadband survey that is located here - there is one survey for domestic use and one for business use, so if you run a business or work from home please do both - and encourage your neighbours to do it as well because the more people that respond from a given area the higher priority it will be.

How close can fibre get to your property?
A (usually) simple way to improve broadband speeds is to put fibre to the BT cabinet. This is a green box by the side of the road which provides telecoms to a village or group of properties. We need to map the exact locations of these boxes so that we can establish what benefits might be gained from this type of upgrade. Please register the location of your BT cabinet and any others you may come across. You can do this here and there is also an App for iPhone or Android so that you can do it whilst you are out and about!
Further updates will be issued on a monthly basis (which I'll also post here). For further information about the superfast broadband project, please click here.

Wednesday, 22 June 2011

Fosse Division Community Forum - 16 June

Latest Thursday night, I attended the quarterly Fosse Division Community Forum meeting in Withybrook where matters affecting, and of interest to, the Fosse area are discussed.

It was nice to see a good turnout from the local area at this meeting: four Shilton parish councillors were in attendance, along with a further five residents from Barnacle. This turnout was principally to hear the item on local policing priorities, which is when the
Rugby Rural North Safer Neighbourhood Team ask members of the public what they would like to see the local police team focus on during the next three months.

The discussion was led by Sergeant Sam Oakley, who heads up the local Safer Neighbourhoods Team. There were a number of suggestions put forward for policing priorities, including carrying out extra patrols to try and curb much of the anti-social behaviour that seems to have increased around the Top Road area of Barnacle recently. The police were supportive of this request and agreed to adopt it as one of their priorities, albeit slightly diluted by rolling it into a wider priority to deter anti-social behaviour in Barnacle, Shilton and Ansty collectively. I hope that proper focus is given to where anti-social behaviour is currently happening, rather than where there are (largely unsubstantiated) community fears that it might be.

Helpfully, the Safer Neighbourhood Team keep a log of the action they have taken in response to this policing priority, which can be viewed
here. At the time of writing, two specific patrols had been conducted by PCSO Matt Havelock on Friday 17 June at 9.50am and Saturday 18 June at 3.20pm. There is a commitment to undertake a minimum of 15 extra patrols during the next three months.

Anna Rose, Head of Planning and Culture at Rugby Borough Council, then gave a presentation on development issues in the borough. These focused on the proposed housing development at the
Rugby Radio Station site in the east of the borough (providing 6,000+ new homes) and the Gateway development site in the north of Rugby town (which will provide a further 1,000+ new homes). Whilst not impacting directly on the Fosse area in themselves, these will be significant housing developments that will meet the future housing needs of the borough up to 2026.

More contentiously, Anna Rose also updated members of the public on the development of wind farms in the borough (the current planning application by
SSE Renewables for nine turbines at Churchover can be viewed here) and on the appeals that have been lodged against Rugby Borough Council's refusal of planning permission for two gypsy caravan sites in Top Road, Barnacle. The first appeal, at land on the south side of Top Road (and known locally as 'Top Park 2') is scheduled to begin on 1 November, with the appeal at the larger 'Top Park 1' site to commence sometime after that date.

Finally, Tonino Ciuffini, Warwickshire County Council's Head of ICT, gave a presentation on the campaign to improve broadband speeds within the county, and
urged everyone to complete a questionnaire on the broadband service that they currently received, as well as what they'd like to receive in the future. I've blogged previously about this questionnaire (which is being organised by the Coventry & Warwickshire Chamber of Commerce, with support from Warwickshire County Council).

The poor broadband line speeds that are being experienced by too many people in the county (including in Shilton and Barnacle) mean that we are increasingly being left behind as more and more public services, as well as social/leisure services, are being delivered on websites that need highspeed broadband availability to make full the use of.

Questionnaires need to be completed by 30 June. Click
here to complete the questionnaire if you a a business, or here if you're completing it as a local resident. I would urge everyone to do this, as it all helps in getting the evidence needed to securing funding to improve line speeds.

The next Fosse Division Community Forum is scheduled for 29 September 2011 at 7.30pm at a venue to be agreed.

Tuesday, 24 May 2011

Business Campaign to Improve Village Broadband Speeds

I noticed this article in the May edition of 'Business Focus' included within last week's Rugby Advertiser newspaper.

Poor broadband speeds in our villages continue to be a barrier to all of us enjoying the full benefits of the internet, and anyone trying to do something about that deserves our support. Therefore, I would urge as many businesses and residents as possible in Shilton and Barnacle to complete the survey on the
Coventry and Warwickshire Chamber of Commerce's website.
Companies feel the need for speed by Peter Ormerod

A Rugby businesswoman is leading a campaign for faster internet connections in the town and surrounding villages.

Leigh Hunt works as an e-business adviser for
Warwickshire County Council and is helping a group of companies and local authorities put together a bid for high-speed broadband across the county. She is now calling on businesses to tell her how the current system is working - or not working.

Leigh said: "Superfast broadband is not just a luxury for businesses. It has become essential. It's impossible to overstate the massive benefit this would bring to the whole economy - especially in our more rural areas, which are currently at a disadvantage because of not being able to use everyday technologies. But we need to know exactly how the current system is working and how it is affecting business to prove that action is needed."

Leigh believes that, as an example, every business and household should be able to use the
BBC's iPlayer without difficulty - something that's not the case at present.

She added: "That's a good benchmark and if we can get the entire sub-region up to speed it would bring huge economic benefits. Even in places like Shilton, businesses have problems.

The campaign is being waged on behalf of
Coventry and Warwickshire Local Enterprise Partnership, which includes councils in Coventry, Warwickshire and Solihull and the Coventry and Warwickshire Chamber of Commerce.

Businesses and individuals wishing to make known their views on the subject can complete a survey at the Chamber's website.

See www.cw-chamber.co.uk for more information.
It's particularly pleasing that the rural areas are recognised as suffering with poor broadband connection speeds, and even better that Shilton is specifically highlighted as an example.

Read more about this
here.

Thursday, 13 May 2010

Broadband Scrutiny Review - Update

You may recall that back in March I reported that Rugby Borough Council had decided not to undertake a scrutiny review into the availability of high speed broadband in the rural areas of the borough. This was a suggestion I had made in response to their request in February for issues of local concern that would benefit from a detailed review by the Borough Council.

Yesterday, I received a letter from Rugby's Scrutiny and Policy Officer setting out in detail the reasons why the Council had decided not to undertake a scrutiny review into this issue.

This is the letter:

Thank you for submitting Shilton Parish Council's interesting proposal for an overview and scrutiny review on access to high speed broadband in rural communities. The members considered a record 33 proposals and reducing these to a manageable shortlist was a challenging task. I have to inform you that your proposal was not selected for inclusion in the scrutiny programme in 2010/11.

The members noted that the issue of slow speeds and non-availability of broadband in rural and many urban areas across the country was currently being addressed through the Broadband Service Commitment. They felt that a national rather than a local approach would in the first instance be most appropriate, and a local scrutiny study would duplicate much of this. In the meantime,
Virgin and BT are known to be doing some work to make improvements in individual areas, and I am sure local councillors will do all they can to act as spokespeople for their areas.

This is as far as the members' discussion of the matter went. However, I would add that, after the completion of the present phase of the national assessment of 'not-spots', it might be worth looking at this subject again. The funding of the national initiative to improve coverage will presumably continue to be problematic, and - given the dire prospects for public funding - this will be no less the case at local authority level. However, if the businesses that will benefit believe there is a good business case for putting up the money themselves, all may not be lost.

You might therefore consider resubmitting your proposal next year, possibly focusing on local initiatives. I would warn, however, that there will still be no guarantee that a case can be made for a scrutiny review. The uneven availability and speed of broadband may be a matter of public concern, but it would be hard to argue that high speed broadband is necessary for social networking and the types of communication with and by the council that are mentioned in support of your proposal. (Admittedly, though, no broadband at all is a different matter.)

In the meantime, there may be work that interested parish councils can do in their localities, for example by gathering evidence so that local businesses would regard putting money into a wireless scheme as a sound investment and, indeed, by co-ordinating schemes funded this way.

Thank you again for your suggestion. We rely on involvement from outside organisations and individuals to keep our overview and scrutiny work relevant to local people's needs and concerns, and I hope you will not be deterred from making other suggestions in future.

I'm grateful to Rugby BC's Scrutiny Office for this considered response but, regrettably, don't entirely share their confidence that the private sector alone can be relied upon to meet the demand in rural areas for highspeed broadband provision.

I shall blog again within the next week on my more detailed response to the issues raised in this letter and the way I think things could evolve for rural broadband provision.

Wednesday, 24 March 2010

No Scrutiny Review of Rural Broadband

At the beginning of February, I blogged about a suggestion I had made to Rugby Borough Council's Overview and Scrutiny Management Board for a review of access to high speed broadband internet in rural communities in the borough.

Rugby's councillors carry out scrutiny reviews into a range of different topics every year, and had called for suggestions from parish councils and members of the public for issues of local concern that they could look into.

I am concerned at the general lack of availability of high speed broadband within Shilton and Barnacle, and the implications this has for members of the public to access services online. The Parish Council supported my suggestion for a scrutiny review to look to establishing the extent of poor broadband provision within rural communities in the borough, as well as investigating what technologies exist that can overcome this problem.

Last week, the Overview and Scrutiny Management Board met to consider which scrutiny reviews to undertake during 2010/11. Sadly, my suggestion was not adopted. It was considered that such a review..... "would duplicate other initiatives, particularly work being carried out by Warwickshire County Council". However, one small positive was that the councillors did accept that the proposal should be considered again next year for a possible review to be carried out towards the end of 2011.

I'm not aware of what "other initiatives" Warwickshire County Council is currently involved with in this regard, but I shall be looking into this to see if there's scope for the issues in Shilton and Barnacle to be considered as part of it.

To be fair to Rugby BC, there were 33 suggested reviews, of which 16 have now progressed for further consideration. However, I shall have to look to pursue the broadband issue through other avenues.

The full report considered by the Overview and Scrutiny Management Board can be read here.

Monday, 1 February 2010

Scrutiny Review Proposal for Rugby Borough Council

Each year, Rugby Borough Council carries out a series of scrutiny reviews on topics of local concern. A number of in-depth reviews are undertaken by small cross-party groups of councillors, who will gather evidence in order to make recommendations for change or improvement to the Council's Cabinet.

In order to assist in drawing up its work programme of reviews in 2010/11, Rugby is asking individuals and organisations (including parish councils) to suggest issues of local concern that would benefit from a detailed review by the Borough Council. With this in mind, over the weekend I submitted my suggested scrutiny review for inclusion within their 2010/11 work programme.

My suggestion is a review of the availability of highspeed broadband internet in rural communities within the borough. It can't have escaped anyone's attention in Shilton or Barnacle that the broadband access is slow at best, at times becoming non-existent. Where broadband is available, line speeds are so slow that making use of services like the
BBC's iPlayer is impossible.

The problem is due to the distance from properties in the two villages to BT's exchange, which is located at Walsgrave. The further the distance between the house and the exchange, the slower the download speeds will be. I'm told my property is 6.1km away from the exchange, which is right at the limit of being able to access broadband services. And unless BT build an exchange closer to the village, things won't improve.

The
Government are recommending that households throughout the country should have access to 2Mbps download speeds by 2012, and have introduced the 50p per month 'broadband tax' on all telephone line rentals to help pay for the infrastructure upgrades that will be required to deliver these improvements. The 2Mbps download speed is considered the minimum required to be able to watch streaming video services like the iPlayer and YouTube. But will these improvements happen before the end of 2012? I very much doubt it.

My scrutiny review would require Rugby Borough Council to establish how many households within the borough are currently unable to access broadband speeds in excess of the Government's recommended 2Mbps. It asks what measures Rugby Borough Council could take to ensure that those households currently without highspeed broadband access were not disadvantaged in accessing public information over the internet. And it challenges the Council to work with technology partners to look at innovative ways to bring highspeed broadband to rural communities within the borough through the use of wireless technologies.

There are many examples across the country where wireless technology has been used to provide the solution to slow broadband speeds. Hopefully, this proposed scrutiny review will help test the extent to which Rugby Borough Council are prepared to work with local communities to overcome pockets of super slow broadband.

Rugby's Overview and Scrutiny Management Board are meeting on 15 March to consider which reviews to take forward into next year's work programme. I shall keep you updated on progress as it develops. Broadband is no doubt a topic I'll return to again at another time!